EMT Practice Test
1. Question Content...
Question1: What portion of Activity B is on the critical path?
Question3: Each of the following accurately describes total float in a schedule EXCEPT:
Question8: Determine the correct formula and date for the late start for Activity 9001.
Question10: What is accurate about Activity 7001 in the precedence diagram?
Question11: Determine the correct formula and date for the late finish for Activity 2002.
Question16: Which of the following is NOT a tool or technique used to perform scope planning?
Question20: Budgeted cost of work scheduled is _______________________.
Question21: Determine the driving activity for Activity 10001.
Question24: When resource leveling craft labor for a critical path schedule, the scheduler
Question25: How many work days does it take to move the product from testing to sale?
Question26: The addition of which of the following relationships would cause a logic loop?
Question29: Determine the correct formula and date for the late finish for Activity 2001.
Question31: Which of the following will always describe the critical path? The path with
Question32: For which of these delays should an owner grant a time extension?
Question36: Which of the following is NOT required when initially planning a project?
Question43: Determine the correct formula and date for the late finish for Activity 6002.
Question44: What is a critical path method schedule?
Question47: An early start constraint dictates
Question49: Project schedules help control all of the following EXCEPT for_____________________.
Question50: What activities are concurrent to Activity 2001 in the "normal" schedule?
Question51: These are the activities on the critical path:
Question52: Who will receive the most benefit from a master schedule of the Spring Highway project?
Question53: Which statement is true?
Question56: Assumptions made during the planning stage should be_____________.
Question57: How much Total Float does drafting the product manual have?
Question58: What is the remaining work duration of Active D?
Question60: What changes to logic would eliminate Activity B from the critical path?
Question63: The BEST reason to use multiple calendars is to:
Question65: A driving relationship is _____________________.
Question66: Estimate to complete (ETC) is __________________.
Question67: All the following describe the critical path of a schedule EXCEPT:
Question69: The work breakdown structure is used to organize
Question70: Identify the late finish to develop plans and specs.
Question73: How could the structural steel drawing delay have been prevented?
Question76: Which of the following statements is true?
Question78: What project cost elements would NOT normally be reflected in the Activity 1000?
Question79: The linear scheduling velocity diagram has the following two-axis:
Question81: Is activity 7001 pictured correctly in the precedence diagram?
Question82: Which of the following is NOT input data to the construction planning process?
