Question1: Which is a purpose of the Business Case theme?

Question2: Which does the Executive need to ensure is in place before the project is initiated?

Question3: Which is NOT obtained from a product's Product Description?

Question4: What product should be used to confirm the version number of ail products in a particular stage?

Question5: Which role is responsible for the management of a risk assigned to it?

Question6: Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.

Question7: Where should a Team Manager look for information on the quality required for a product?

Question8: Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ?
] the project's plans

Question9: Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity

Question10: Identify the missing words in the following sentence.
Configuration management typically includes [ ? ] as one of the five core activities.

Question11: Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Question12: Which is a type of issue?

Question13: Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

Question14: Which of the following are typical core activities within configuration management?
1 . Planning
2 . Risk assessment
3 . Verification and audit
4 . Identification

Question15: When considering risks, which describes an opportunity in a project?

Question16: Who does the Team Manager report to and take direction from?

Question17: Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.

Question18: What is the definition of a project outcome?

Question19: Which task is performed by the Change Authority?

Question20: Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

Question21: Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Question22: Which statement is FALSE?

Question23: If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?

Question24: Which is a purpose of a Lessons Log?

Question25: Which of the following is NOT an event-driven control?

Question26: Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Question27: Which is a true statement about time-driven controls?

Question28: How should the Team Manager report that tolerances are forecast to be exceeded?

Question29: What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

Question30: When are tolerances for a Work Package agreed?

Question31: Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Question32: Which is a purpose of an Issue Report?

Question33: Which should be funded from a change budget?

Question34: Which is a responsibility of a Team Manager?

Question35: Which statement about the Directing a Project process is true?

Question36: Which document should record the agreed amount of risk budget for a project?

Question37: Which is one of the three levels of plan in PRINCE2?

Question38: Which is an objective of the Directing a Project process?

Question39: What is a purpose of a Benefits Review Plan?

Question40: Which is a purpose of the Project Product Description?

Question41: Which may be funded from a risk budget?

Question42: Which is a purpose of the Risk theme?

Question43: How many management stages should a PRINCE2 project consist of?

Question44: What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Question45: Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

Question46: Which product documents the information needed to demonstrate continued business justification?

Question47: What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Question48: What do acceptance criteria identify?

Question49: Which statement about risks is FALSE?

Question50: Which of the following is NOT part of quality control?

Question51: Which is a purpose of the Risk theme?

Question52: Which is NOT considered when defining risk tolerance?

Question53: Which is a purpose of a Project Brief?

Question54: Which is a purpose of the Risk Register?

Question55: Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?

Question56: Whose approval is needed to replace a Stage Plan with an Exception Plan?

Question57: How is a Benefits Review Plan used in the Closing a Project process?

Question58: Which project characteristic suggests that projects should have a defined start and a defined end?

Question59: What do customer's quality expectations identify?

Question60: Which statement about the Directing a Project process is FALSE?

Question61: Which process provides the Project Board with the information it requires in order to commit resources to the project?

Question62: Which is a valid statement about the Project Support role?

Question63: During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

Question64: Which is a difference between management and technical stages?

Question65: Which is a true statement about acceptance criteria?

Question66: Why is the Initiating a Project process used?

Question67: Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.

Question68: Which is NOT confirmed during the Initiating a Project process?

Question69: Which characteristic distinguishes a project from regular business operations?

Question70: Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

Question71: Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.

Question72: Which plan provides the Business Case with costs during the Initiating a Project process?

Question73: Which is a purpose of a Risk Register?

Question74: What product records any time tolerances agreed between the Project Manager and Team
Manager?

Question75: Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,

Question76: Which is performed as part of the recommended risk management procedure?

Question77: Which is a typical core activity within configuration management?

Question78: Which may be funded from a risk budget?

Question79: Which is a benefit of using PRINCE2?

Question80: Which is a purpose of the Controlling a Stage process?

Question81: Which is an objective of the Starting up a Project process?

Question82: Which product records any project outcomes perceived as negative by stakeholders?

Question83: Identify the missing words in the following sentence.
At an agreed frequency, a Team Manager will send a [ ? ] to the Project Manager.

Question84: Which task is performed by the Change Authority?

Question85: Which is part of quality control?

Question86: Identify the missing word(s) in the following sentence.
During a quality review meeting [ ? ] any identified defects.

Question87: Which is a purpose of a Configuration Management Strategy?

Question88: Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.

Question89: When should the Project Board refer to corporate or programme management for a decision?

Question90: Which role is responsible for creating Checkpoint Reports?

Question91: Which is a PRINCE2 time-driven control?

Question92: Which is an objective of the quality review technique?

Question93: What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Question94: Why does PRINCE2 recommend three different levels of plans?

Question95: Who carries out audits that are independent of the project?

Question96: Which is a purpose of an End Stage Report?

Question97: Which process is used by a Team Manager to coordinate work on one or more of the project's products?

Question98: Which is an objective of the Directing a Project process?

Question99: Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

Question100: Which is NOT a PRINCE2 principle?

Question101: Which is a true statement about PRINCE2 event-driven controls.

Question102: Which is a recommended quality review team role?

Question103: Which is NOT one of the levels of plan recommended by PRINCE2?

Question104: During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

Question105: Identify the missing words in the following sentence. The purpose of the Starting up a
Project process is as much about [?] as it is about requesting authorization to initiate viable projects,