1. Question Content...
EXPLANATION
Answer: X - EXPLANATION Content.
Question1: When managed correctly, the balanced scorecards can change the way an organization does business.Balanced scorecards keep focus on results. As a portfolio manager, you use the balanced scorecards while developing the Portfolio Management Plan in order to
Question2: You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the communication closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust Communication management plan. What is the result of developing this plan?
Question3: You are in the toughest phase of the portfolio life cycle due to the governmental issues in your country.Yesterday night, one of the key team members quit and left the country. You have included this in the portfolio risk register while planning the portfolio because you knew that this could happen and that this key resource has family in Canada and can leave if the situation gets bad. Following this, you activated the response plan, which is to initiate a new component that will cater for reaching the deliverable in another way.However, an immediate approval is needed for initiation of this component or the end-of-month major deliverable will be delayed. To whom you should present the proposal for urgent approval?
Question4: You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. When it comes to Managing portfolio risks, a risk owner, along with the portfolio manager, should select the strategy or mix of strategies most likely to be effective. Which of the following is not a risk strategy?
Question5: The Strategic Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Strategic Plan purpose and focus?
Question6: You are mid-way through your portfolio and you are approaching a major milestone where multiple components will be authorized for execution and implementation. For informed decision making, as a portfolio manager, you will be communicating reports that will be viewed and analyzed, and used as critical information for taking a decision for the authorization of components. After passing through the authorization process, multiple reports are generated and others are updated. What type of reports is generated from this process?
Question7: A junior Portfolio manager has come to you for advice. She is asking about her main responsibilities as a portfolio manager in order to see if she is on the right track. What should be your advice to her?
Question8: The Portfolio Performance Management Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Performance Management Plan purpose and focus?
Question9: In a portfolio, data is an abundant asset, and managing the information aiming for a a better decision making is critical. For this you use a variety of Quantitative and Qualitative analysis methods. These methods are performed in 4 of the portfolio management processes and serve a slightly different purpose in each and every one of them. Considering that you are currently performing risk assessment and handling risk responses, how can you make use of the quantitative and qualitative analysis?
Question10: Risks perspectives differ within the organization between executive management, operations management, portfolio management and project/program management. When it comes to Operations management, which of the following is a risk concern?
Question11: Your CEO is keen to know the expected value of multiple components that interest him and wants you to give him a comparison of the expected value across components. You are currently looking for a tool to facilitate comparison of expected value across components and support informed portfolio decision making. What are you looking for?
Question12: Portfolios have a lot of components in them and are executed along an extended lifecycle. For this, as a portfolio manager, you continuously monitor and control the progress and status. What input can you use to help you with this?
Question13: The sponsor came to you asking for a high level timeline to depict the approach that you will take to execute this portfolio. What tools and techniques is useful in your case?
Question14: As part of the portfolio communication management, multiple documents are prepared in order to effectively manage communications. The Communication Calendar is one of the prepared documents, what does it include?
Question15: Your team members were having a discussion about the contents of the Portfolio Charter and they came to you for advice because they could not agree on a common answer. What would be your advice to them?
Question16: You have been newly appointed as a portfolio manager and found out that your predecessor did not develop a Portfolio Risk Management plan as he thought that it is not necessary in the case where he has a risk register.One of your first activities was to develop the missing plan. To do this, you needed to consult with stakeholders in order to fetch risk information in order to identify risks and plan risk management. Which of the following inputs to this process will help you in identifying which stakeholders to analyze?
Question17: Portfolio managers tend to use the efficient frontier analysis as a modeling approach that gives decision makers the analytical tool to optimize portfolios given resource constraints such as risk. In which of the Portfolio management processes the efficient frontier is mostly used
Question18: Your sponsor is under a lot of pressure from the management because the portfolio has been hit by multiple risks already and the situation is going towards its termination. Your sponsor asked you to prepare him an analysis to show the probable ROI and the confidence level in it. Which approach is the best one in this case?
Question19: A major strategic change has occurred and you are managing the change at portfolio level. You are currently performing gap analysis and you receive information on a stakeholder that is extremely unhappy with how the change will be handled in your portfolio. What should be your best course of action?
Question20: During one of the management meetings, an opportunity was identified. This opportunity has a huge impact on the portfolio. What is your first action as a portfolio manager?
Question21: A portfolio manager on one of the major sub-portfolios in your portfolio has tendered his resignation and gave you a 2 months notice. This unexpected change will require you to take immediate action with the governance board. Which of the following processes will be handling this situation?
Question22: You are managing a large construction portfolio. Recently, and due to budget cuts, you have been having resources issues on multiple initiatives and has been struggling with maintaining a healthy resource allocations. You are currently analyzing the capability and capacity for scarce machinery resources shared across three major programs in the portfolio. What are you currently applying?
Question23: As part of the new strategic direction, the executive management has decided to create a portfolio for the development of a new product. You have been assigned as the portfolio manager. What should you do as a first step?
Question24: Establishing a portfolio management process starts with the development of the organizational portfolio management implementation plan. Which of the following helps while developing this plan?
Question25: Portfolio Reports are widely used as inputs and outputs to multiple processes throughout the Portfolio Life Cycle. Which of the following is NOT part of portfolio reports?
Question26: In a portfolio you have a continuous interaction between the portfolio and its components. The approach is top down when it comes to offering guidelines and approaches and becomes bottom up when the components report status and progress to the portfolio. What is the relation between the portfolio and portfolio components when it comes to defining the performance measures and targets (metrics)?
Question27: You have set a series of meetings with your portfolio team members as an answer to the identification and update of the organization near-term budget and plans. As a result you have defined and developed the portfolio strategic goals, near-term budgets, and plans, and you now want to start managing ongoing portfolio activities. What is the focus of what you are doing?
Question28: Two functional managers within your portfolio are arguing about one scarce resource, and each one is claiming that the resource should be assigned to them. What should you do as a portfolio manager in order to solve this issue?
Question29: As part of developing the Communication Management Plan, a portfolio manager executes the Communication Requirements Analysis, in addition to Stakeholders Analysis. Which of the following options in your opinion is a result of the Communication Requirements Analysis?
Question30: Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. When it comes to risk tolerance definition, which of the following is the correct one?
Question31: Due to strategic changes, one of the sub-portfolios in your portfolio has been decided to be canceled because it no longer meets the new market demands. What is your next step as a portfolio manager?
Question32: You have just finished the development of the Portfolio Communication Management Plan. The portfolio team is looking for portfolio value assessment, status reports, and portfolio forecast with variance to plan. Where should they find this information?
Question33: Following an organizational change and restructuring. One of the Portfolio Key Stakeholders got a promotion and became a director. She became less interested in your portfolio and you used to engage her very closely.What is your best course of action in this case?
Question34: As a portfolio manager, you map the business value areas to each component in your portfolio in order to maintain alignment with the organizational strategy. What is the mechanism that will be used for tracking areas of measurement for assessing how the mix of portfolio components is performing?
Question35: A junior Portfolio manager has come to you for advice. He is hearing a lot about the focus of portfolio management practices, however, he is not sure anymore of the exact answer. What do you, as an experienced portfolio manager tell him?
Question36: Which of the options is considered part of Enterprise Environmental Factors (EEFs)
Question37: Along the course of the portfolio, you will be recommending the initiation, termination and update of components. The governance bodies will be approving or rejecting your recommendations as part of their role in the authorization of the portfolio. As a portfolio manager, which of the following, in your opinion, is the objective/purpose of the Authorize Portfolio Process?
Question38: One of your team members came to you asking about the risk "Watch List"; he heard this term in a meeting on risk analysis and did not know what it meant. What will your advice to your team member be?
Question39: Portfolio managers tend to use the efficient frontier analysis as a modeling approach that gives decision makers the analytical tool to optimize portfolios given resource constraints such as risk. Consider that your company is risk-averse, on which side of the efficient frontier curve should the undertaken portfolios lie?
Question40: Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. When it comes to managing portfolio risks, which of the following activities is used
Question41: Strategies are changing, the portfolio mix is changing, the portfolio is progressing and you are doing a great job optimizing the mix of components. What tools and techniques are you using in the case?
Question42: You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust performance management plan. What is expected to be found in this plan?
Question43: A new project manager was given an assignment on one of the components in your portfolio. What will you do as a portfolio manager in order to align the project manager with the strategic direction and integrate him/her with the work in progress?
Question44: A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. For this, you are always on the lookout to optimize your portfolio. What can you use to start this process?
Question45: As a portfolio manager, you realize the importance of communication for the success of a portfolio. You are now developing the portfolio management plan and are looking for the portfolio current risks status including high risks. Which of the following contains what you are looking for?
Question46: You have been receiving complaints from Key Stakeholders about multiple projects not being initiated, also they have great strategic alignment. What should have been done to avoid this?
Question47: The portfolio undergoes a lot of changes through the portfolio life cycle, and the state of the portfolio changes on the go. Some components are terminated, other are added and initiated. When it comes to the authorize portfolio process, which of the following represents the state of the portfolio
Question48: A junior Portfolio manager has come to you for advice. He is hearing a lot about the definition of portfolio management, however, he is not sure anymore of the exact one. What do you, as an experienced portfolio manager tell him?
Question49: Optimizing the portfolio is a major recurring process that the portfolio manager performs throughout the portfolio life cycle in order to balance the mix of portfolio components. During this process, the portfolio manager uses a number of graphical analytical methods to help him ease the process. Which of the following is not a graphical analytical method used in this process?
Question50: Which of the following depicts the use of the burn-down and burn-up charts?
Question51: While managing the portfolio value, it is important to know the different roles of responsibilities and accountabilities for the actual benefits realization in order to be able to aggregate the correct value from different components; in which document are these roles and responsibilities mentioned?
Question52: Stakeholders expectations and requirements change throughout the portfolio life cycle. New stakeholders can be added or removed and requirements need to be continuously solicited in order to keep the portfolio aligned with stakeholders expectations. What is the process for soliciting requirements called?
Question53: A portfolio manager needs to continuously balance the need and requirements with the available resources to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. When it relates to developing the charter, and in order to complete the portfolio structure, the capability and capacity analysis is used to
Question54: The portfolio management information system is often a collection of spreadsheets rather than automated tools. An effective PMIS enables the portfolio manager to define, analyze, design, produce, and manage information systems to support a successful portfolio, and includes tools and processes such as:
Question55: In a portfolio you have a continuous interaction between the portfolio and its components. You have to follow a lot of processes and procedures in order to reach a satisfactory result. In your opinion as a portfolio manager, who guides the portfolio team to follow the processes, metrics, and other procedures in the portfolio?
Question56: You are the portfolio manager for a large and complex portfolio with a low risk appetite. You are currently planning for risk management, multiple investment choice tools are used as part of the quantitative and qualitative analyzes. Which of the following tools focuses on pricing and sales forecast?
Question57: Portfolio Prioritization Model is included in the Portfolio management plan and guides the ongoing decisions as to which portfolio components should be added, terminated, or changed; which of the following is correct regarding the Prioritization Model purpose and content?
Question58: While managing portfolio communications, the portfolio manager needs to account for the communication needs of the component teams in order for them to stay in the loop of the big picture. Which of the following can be of interest to this group of stakeholders?
Question59: After a strategic change is managed and finalized, you as a portfolio manager, are expected to document changes to the portfolio components attributes. Which of the following is the document in which you document these changes?
Question60: You are the portfolio manager in a large organization including a diversity of stakeholders. From the start, you knew the importance of correctly managing the stakeholders requirements and concerns and you grouped them in order to
Question61: The interest, influence, and communication needs of business operational stakeholders who are looking to ensure alignment between portfolio components, while minimizing negative impact and maximizing positive benefits of all portfolio-managed changes to their business operations, relate to which type of stakeholders?
Question62: You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. A major risk has recently occurred and the risk owner came to you asking advise on how to report it. what would you advise her?
Question63: Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. You are currently assessing risk against multiple criteria and classifying them as part of developing the risk management plan. Which of the below reflects what you are doing?
Question64: Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, change to reflect the portfolio new vision?
Question65: You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The Portfolio Roadmap is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Roadmap purpose and focus?
Question66: You work in a fairly small company where the PMO helps in providing oversight to support the portfolio management. In such organization, where are the PMO structure, responsibilities, and implementation approach documented?
Question67: You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. You are currently defining the portfolio and with the purpose of
Question68: Managing Strategic Change is an integral part of any portfolio in order to remain aligned with the strategic objectives. Your portfolio has undergone a major strategic change and you are currently determining the volume of work required to do in order to re-align the portfolio. What are you currently using?
Question69: While managing portfolio value, you met with stakeholders and discussed how to address the strengths and weaknesses in order to ensure benefits are comprehensively and holistically taken into consideration. Which of the following tools and techniques are you performing?
Question70: You have been asked to be the manager for a governmental portfolio, and your starting point should be tendering a strategic plan to the board for validation and approval for continuation. Which documents/artifacts do you have debuting the portfolio that you can use to develop the strategic plan?
Question71: A number of components proposals are on the table as a result of the strategic planning cycle. While defining the portfolio, you wanted to make a preliminary screening of the proposed components in order to filter them based on the acceptance criteria. Which of the following techniques you use?
Question72: Consider you have the following efficient frontier graph with multiple portfolios on it. Which portfolio do you choose?Larger image
Question73: As part of the Portfolio Communication, the Portfolio Manager analyzes the raw data assimilated from the portfolio process assets and from the stakeholder analysis. This analysis aims to isolate the data that hold value to the receiving audience. Which tool can the portfolio manager use to help him in performing this analysis?
Question74: A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. You are currently using it in the development of your charter. What is its purpose in this case?
Question75: In managing strategic change, the portfolio manager performs stakeholder analysis in order to consider the changing requirements. Which of the following options is referenced in this case to provide guidance on the communication required to ensure successful change?
Question76: Developing the Portfolio Management Plan is a major step in a Portfolio and for a Portfolio Manager. You are currently developing this plan and having focus groups and brainstorming activities during which you are using mind-maps diagrams to organize the idea into logical groupings. Which of the below are you using?
Question77: You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. Risk Categories, criteria and probability and impact are updated as a result of Developing the Risk Management Plan. These updates are recorded in which of the following?
Question78: Your company has decided to invest in a revolutionary product that will make the delivery of online orders easier and will cut down the delivery time by no less than 35%. While measuring the value of the new component with relation to the market, which of the following should be used?
Question79: Updates to schedules i.e. resource, funding, benefits, are results of Developing the Portfolio Performance Management Plan process. Where should these updates be recorded?
Question80: As you grow older, you gain more experience and things that once seemed hard to assimilate, can become very easy. One junior member of your portfolio management team is confused on the relationship between the Optimize, Authorize and Provide Oversight processes. What could your advice to him be?
Question81: Along your portfolio lifecycle, you have been conducting multiple review meetings to ensure continuation from one phase to another and to ensure the alignment and value delivery, in addition to communicating decisions and valuable information to the related stakeholders. Changes to the approach of portfolio governance may be a result of review meetings. Which of the following options include updates to the governance model?
Question82: During the portfolio lifecycle, components will be authorized, initiated, executed and closed accordingly. For authorizing the portfolio, as a program manager you will use which of the Which of the following tools and techniques?
Question83: Calculate the composite index for the following portfolio having CPI weight = 80% and SPI weight = 20% Larger image
Question84: Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. Risk is part of project, program and portfolio management and has a different exposure in each and every one. Which of the following highlights this difference?
Question85: You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. For this you maintain a risk register. The risk register is used throughout the portfolio life cycle in order to track and manage risks. It is continually updated throughout the portfolio life cycle. As a portfolio manager, you know that the risk register includes all of the following except
Question86: In a portfolio, data is an abundant asset, and managing the information aiming for a a better decision making is critical. For this you use a variety of Quantitative and Qualitative analysis methods. These methods are performed in 4 of the portfolio management processes and serve a slightly different purpose in each and every one of them. When it comes to the optimizing portfolio, what is the purpose of using this analysis?
Question87: Organizations pass by a strategic planning cycle on regular basis in order to align existing strategies, remove strategies and add new ones. When it comes to the implementation, which of the following options represents the activities through which the organizational strategies are implemented?
Question88: Stakeholders have complained to you that they are receiving redundant information and they prefer that you fix the issue promptly as it is time consuming for them. What is your best course of action?
Question89: You have just finalized aggregating value from the ongoing components to present a consolidated report to the governance board, in addition to recommending changes to portfolio and information to enable a better decision making. You are now looking for a place to document updates including new measures, reports and processes for effective ongoing management of the portfolio value. In which of the following documents are these measures included?
Question90: One of the stakeholders of one of your components came to you complaining that his manager is not receiving specific information on multiple components progress. What is your best course of action?
Question91: You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. The Portfolio Risk Management Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding its purpose and focus?
Question92: In a portfolio, data is an abundant asset, and managing the information aiming for a a better decision making is critical. For this you use a variety of Quantitative and Qualitative analysis methods. These methods are performed in 4 of the portfolio management processes and serve a slightly different purpose in each and every one of them. Considering that you are currently working to ensure resource capacity is optimally allocated against resource requirements or demand based on known organizational priorities and potential value, how can you make use of the quantitative and qualitative analysis?
Question93: You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust performance management plan. What is the expected result from developing this plan?
Question94: As part of the strategic alignment, you Evaluate organizational strategic goals and objectives using document reviews, interviewing, and other information gathering techniques in order to
Question95: A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. When it relates to managing the supply and demand , what is the purpose of using this analysis?
Question96: While defining the portfolio, the portfolio manager uses a set of evaluation criteria in order to generate a list of portfolio components for optimization and balancing. Which of the following is not an evaluation criteria?
Question97: The portfolio manager defines the portfolio based on a listing of already existing work in the organization and selects the right components in order to be able to prioritize them. What do you use for defining the portfolio based on the listing of work?
Question98: You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. The Portfolio Process Assets are important and referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Process Assets purpose and focus?
Question99: One of your portfolio team members is confused on the reason behind using the three processes: Define Portfolio, Optimize Portfolio, Authorize Portfolio and Manage Portfolio value. For him, we can skip a couple of processes. He came to you for advice. What should be your response to him?
Question100: You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. For this you start by developing the strategic plan. What output do you expect from this process?
Question101: While aggregating data from component reports in order to present the portfolio status to the governance board on an upcoming review meeting, which of the following is the most important thing to do?
Question102: You have been recently assigned to manage a new portfolio that is supposed to shift the company from silo-based to a projectized one. You are in the process of initiating the portfolio. You are currently developing the strategic plan. Upon finishing it, you are expected to present
Question103: The Scenario Analysis is used twice as a tool and technique, once while developing the charter and another time while managing Supply and Demand (It also exists as part of the quantitative and qualitative analysis as part of the optimize Portfolio process). When it comes to Manage Supply and Demand, which of the following represents a correct description of the Scenario Analysis?
Question104: When it comes to change, one of your junior portfolio managers came to you requesting your help to deal with the overwhelming strategic changes. He wants your assistance in solving the issue of continuous changes in the organization's objectives. What should be your advice to him?
Question105: Due to market technological changes, your company got impacted and was urged to revise its portfolios. You are currently revising your portfolio to determine the required changes in the component mix. Which of the following options helps in comparing the current portfolio mix to the new strategic direction in order to determine the needed changes?
Question106: A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. When it relates to optimizing portfolio, what is the purpose of using this analysis?
Question107: One of the key stakeholders came to you asking you to add more metrics because she thinks that it would give the portfolio management a better view of the actual progress. For her the more metrics you have the better.What should your opinion be regarding this?
Question108: One of the major resources on your portfolio is needed by two of the components at the same time. This resource has high technical knowledge and is aware of all the business needs. Which of the following tools and techniques can you use in order to solve this issue?
Question109: Portfolio Governance is important in a portfolio to maintain correct alignment, monitor and control performance and status, reshuffle the mix of components as found necessary, etc. Governance management includes which of the following processes?
Question110: Multiple communication methods are used by the portfolio manager in order to proactively convey messages and engage the stakeholders at the right time and in the right manner. Which tool is used to visually convey multiple messages at the same time?
Question111: You are the manager for a major industrial portfolio aiming to rebuild the vintage building in your region.Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budget, you know that you will be managing the portfolio closely and that the governance board and the stakeholders would want to check on the progress and status frequently. For this you started to develop a robust Portfolio management plan. Which of the following can be used when starting this process?
Question112: Managing Strategic Change is an integral part of any portfolio in order to remain aligned with the strategic objectives. Your portfolio has undergone a major strategic change and you are currently determining if, when, what, and how of implementing the change in order to re-align the portfolio. What are you currently doing?
Question113: While performing the manage supply and demand process, one of your sub-portfolio managers came to you asking advice on how to analyze intangible assets such as resources knowledge or skills based on the metrics defined. What should be your advice to him?
Question114: Your portfolio is on a tight deliverables and is considered the major portfolio in your company. Stakeholders are concerned about the purpose of defining a portfolio while already having an inventory of work and are worried that this will cause a lot of time to be wasted. What is your advice to the stakeholders?
Question115: The existing portfolio manager was replaced by a new portfolio manager and the analysis has shown that the distance between the pessimistic and best case scenario of the new portfolio manager is larger than the old one, which kind of manager is the new one?
Question116: Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. Risk is part of project, program and portfolio management and has a different exposure in each and every one. When it comes to Managing portfolio risks, a risk owner, along with the portfolio manager, should select the strategy or mix of strategies most likely to be effective. Which of the following may be the responsibility of a risk owner when it comes to managing risks?
Question117: Your team members were having a discussion about the purpose behind the development of the Portfolio Charter and they came to you for advice because they could not agree on a common answer. What would be your advice to them?