EMT Practice Test
1. Question Content...
Question2: The number of units produced during a designated time period.
Question10: 365 days x 24 hours = 8760 hours per year. → Average Availability
Question11: = Training Hours ÷ Number of Maintenance Employees → Maintenance Unit
Cost Formula
Question13: During design → PM schedule compliance should be equal or greater than 95%.
(T/F)
Question14: Utilization Time % × Availability % × Performance Efficiency % × Quality Rate %
Question17: = Scheduled Downtime + Unscheduled Downtime
Question18: (%) = [Preventive Maintenance Cost ($) ÷ Total Maintenance Cost ($)] × 100
Question20: Lagging and Leading
Question22: Which inventory system requires regular physical inventory counts?
Question26: Which of the following is a major benefit of enterprise resource planning systems?
Question27: Mesh the production schedule and the maintenance schedule.
Question28: What is the most common reason for adopting a Total Quality Management system?
Question29: (%) = (Corrective Maintenance Cost ×100) ÷ Total Maintenance Cost
Question30: Weibull (life data) analysis is primarily used for?
Question38: (%) = (Preventive Maintenance Hours ÷ Total Maintenance Labor Hours) × 100
Question41: 365 days x 24 hours = 8760 hours per year.
Question44: The number of units produced during a designated time period. → Availability Formula
Question47: (%) = [Business Benefits ($) ÷ Training Cost ($)] × 100
Question49: Operating time (hours) ÷ Number of Failures → Mean Time Between Failures (MTBF) Formula
Question52: O&M → RCM Methodology can't be used effectively on new systems
being designed. (t/F)
Question54: A∞ = lim At t → ∞
Availability is a function of:
Question64: % = {Uptime (hrs) ÷ [Total Available Time (hrs) - Idle Time (hrs)]} x 100
Question65: Operating time (hours) ÷ Number of Failures
Question68: = Total Maintenance Cost ÷ Standard Units Produced
Question73: % = [Condition Based Maintenance Cost ($) ÷ Total Maintenance Cost ($)] × 100
Question74: (%) = (Corrective Maintenance Hours × 100) ÷ Total Maintenance Labor Hours
Question79: Which of the following tools of analysis ranks problems by importance?